Projects: 140km 8″ Propylene Pipelines
Project Outline
140km
Contaminated with oil
Removal of oil
Clean & Dry
No damage to equipment & environment
Depressuring the nitrogen in the receiver
Pipeline cut out prior to cleaning. Note the oil layer.
Solvent and debris collection tank at the receiving site
Cleaning tool damaged by a valve that was not fully open
Batching tool after 140km
Brush cleaning tool after 140km
Various type of tools used for the project
Catching net for moulded foam tools
Receiving site
Receiving site
Temporary wash facility for cleaning tools